Infor LX/BPCS Tips & Tricks for OPERATIONS: New IDF Inquiries

Operations:

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities
Previous Article Infor LX / BPCS Tips & Tricks for FINANCE
Next Article Infor LX/BPCS Tips & Tricks for TECHNOLOGY: New Features in 8.4.2
Print
194 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).

FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.