BPCS/LX Tip of the Week: SFC600

In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.
Previous Article BPCS/LX Tip of the Week: Downtime Reasons
Next Article Baan/LN Tip of the Week: Aborted Finalization Run
Print
78863 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).