BPCS/LX Tip of the Week: The Item Master Requirements Code

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).


Other options for the field are:

1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.
Previous Article Hoffmaster Selects Crossroads MES for LX Implementation
Next Article Baan/LN Tip of the Week: Printing Pick Lists
Print
65138 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

FirstLast

Tips: LN | Baan

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. ...

Use this session to define or maintain cash flow statements and hierarchical structures of cash flow reasons for cash flow statement reports. 

On the Cash Flow Reasons by Statement tab, you can select cash flow reason groups and cash flow reasons to build a hierarchical structure of cash flow reasons for the cash flow statement report.

To link a child cash flow reason group to a parent cash flow reason group:

Categories