Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i
Next Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Print
83605 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3


In Infor LX you need to determine how inventory will be moved in and out of warehouse storage locations, and which of the following transactions to use for inventory control:


  • A transfer transaction can be used to move inventory from one warehouse location to another warehouse location.
  • A production receipt transaction is used to add inventory to a warehouse location.
  • A material issue or backflush is used to reduce inventory from a warehouse location.
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
FirstLast

Tips: LN | Baan

Categories