BPCS/LX Tip of the Week: The Item Master Requirements Code

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).


Other options for the field are:

1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.
Previous Article Hoffmaster Selects Crossroads MES for LX Implementation
Next Article Baan/LN Tip of the Week: Printing Pick Lists
Print
65510 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).

These programs are used to capture and post shop floor information. Labor reporting, machine time, etc. can be captured by either program. The key difference is that one will also capture the production receipt and backflush components. Based on your company information / transaction process, one of these programs will most likely be used daily to capture current shop floor data. You can use the shop packet labor ticket for the manual recording, and the keying of the data. Alternatively, you can incorporate an automated method like an MES solution to capture the data and streamline the process.

FirstLast

Tips: LN | Baan

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.