Infor LN & Baan Tip: What is the GRNI Reconciliation Process?

What is the GRNI (Goods Received Not Invoiced) Reconciliation Process?

The reconciliation process of the GRNI transactions consists of the following steps:

  1. Close the financial period so that no new transactions can be entered.
  2. Print the trial balance.
  3. Print a report of the invoices to be received.
  4. Compare the reports.
  5. Print the reconciliation data.
  6. Examine the reports.
  7. Rebuild the History.
  8. Print the trial balance and the reconciliation report again.
  9. Print the GRNI reconciliation checklist.
  10. Check the balances on the GRNI reconciliation checklist.
  11. Analyze the reconciliation data.
  12. Make corrections.
  13. Print the GRNI reconciliation checklist again.
  14. Post the reconciliation correction transactions.
  15. Accept the reconciliation data.


Have questions on this process or need some help? Contact us! Our experienced Finance consultants will be glad to assist you.

800.762.2077

Previous Article Infor LX & BPCS Tip: Capacity Planning – Resource Requirements Reports
Next Article By 2026, 75% of organizations will base their digital transformation model on the CLOUD!
Print
26539 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

FirstLast

Tips: LN | Baan

Categories