Baan/LN Tip of the Week: Use of Calendars in LN

  • In the Enterprise Modeling Management module in Common, you can define the calendar of companies (company calendar) and enterprise units.
  • In the People module, you can link calendars to teams of employees. The Hours and Expenses module in the People package uses this information to get the default number of hours from the calendar lines.
  • In Common, you can link calendars to business partners and addresses; Procurement and Sales use this information when planning goods transfers.
  • In Manufacturing, you can link calendars to work centers. The work centers' working times determine the available production capacity.
  • In Warehousing, you can link calendars to warehouses.
  • In Service, you use calendars to specify when a cluster is available for servicing.

 Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: At a Loss?
Next Article Save the Date: LX Communities WebEx- Shop Floor Application hosted by Crossroads RMC - March 14, 2017 - 10:00 AM CST
Print
68095 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

FirstLast

Tips: LN | Baan

In typical LN REST API integrations, permissions and authorizations are not implemented or rarely used. To ensure smooth data exchange and avoid errors, it is recommended to disable the authorization and security settings.

Recommendation:

  • In the Authorization and Security Parameters session (tcsec0100m000):

    • Clear the Authorization and Security Enabled check box.

    • Clear all check boxes under Authorization Enable for on the Enabling tab.

Why This Matters:

  • Enabling authorization and security without proper setup can lead to errors and blocked transactions during integration.

  • For example, work center permissions may interfere with:

    • Creating new shifts

    • Booking machine hours

    • Read more