OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
27797 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 