OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
27801 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Defining the Product Routing first requires the items to be setup in the Item Master file. Other master files also need to be defined prior to creating the routing.
These include:

  • The Facility defined with a SYS program
  • The Warehouses defined with an INV program
  • Locations defined with an INV program
  • The Machines (required if using capacity planning or an MES interface) defined with an MDM program

After the above data is set up, the Department file and Work Center files can be setup in MDM. Now you are ready to define a product route.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

 

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.