Baan/LN Tip of the Week: Negative Inventory

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

Previous Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Next Article PDIC Goes Live with Crossroads MES
Print
105320 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

FirstLast

Tips: LN | Baan

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. ...

Use this session to define or maintain cash flow statements and hierarchical structures of cash flow reasons for cash flow statement reports. 

On the Cash Flow Reasons by Statement tab, you can select cash flow reason groups and cash flow reasons to build a hierarchical structure of cash flow reasons for the cash flow statement report.

To link a child cash flow reason group to a parent cash flow reason group:

Categories