Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Anthony Etzel
/ Categories: ERP News, Event / News

Why should you look at OTTO? Let’s see what an OTTO customer has to say:

"When first introduced to OTTO, for on-time ordering, you could not prove to me that there was a better system out there than what we already had. Boy what a big wakeup call! Being in a very option intensive business and the economy in a very flat or negative state, OTTO is the BEST tool to quickly respond to a customer’s needs TODAY. When Millions of dollars are at stake each month, we have to be better prepared to meet the task at hand with fewer people. OTTO is really doing this for us!  What normally took us hours or days to identify several indented bill of material shortages now only takes a few moments with the OTTO program. What this really means is that, we do not have to wait for MRP to run each week to plan and reschedule orders. This can be done today!  What I’m really saying is that, we can advise Purchasing and Scheduling TODAY without waiting for TOMORROW.  We are now able to ship DOLLARS this month and satisfy our CUSTOMERS. Without OTTO in some cases, the Customer would have to wait until next month and potential revenue dollars lost for the month."  Gary Hawk, Planning Manager - construction equipment

Previous Article Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX
Next Article Crossroads RMC Forms Strategic Partnership with CTN Global
Print
33608 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.