BPCS/LX Tip of the Week: Additional Electronic Signature Controls

Electronic Signature Controls have been expanded to include additional programs, files and fields.  

When manufacturing work centers are updated through Work Center Maintenance (CAP100), the system can now require Electronic Signature processing to complete the process. This enhancement allows for broader Electronic Signature controls.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: Problems With Staying on an Old Porting Set
Next Article Baan/LN Tip of the Week: Financial Year End – Have You Done All You Need To Do?
Print
34294 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.