Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor ERP Tip: Top 5 Ways Modern Analytics Reduces Spreadsheet Risk & Inefficiency

Infor LX | BPCS | Infor LN | Baan

Spreadsheets are often the tool of choice for many organizations to store and arrange information for financial planning, analytics, compliance, and more. Ironically, for many business processes that involve managing data, it creates the exact opposite effect––silos of information and inefficiency. And because it stores organizational data in a readily sharable way, there is a high risk of exposing confidential information.

Read this Infor best practice guide to discover the top five business processes that a modern data and analytics architecture can automate and deliver far more value than spreadsheet-driven techniques.

Infor Best Practice Guide: 5 Ways Modern Analytics Reduces Spreadsheet Risk and Inefficiency

Previous Article Infor LN & Baan Tip: Cost Component Setup
Next Article Infor Customer Meeting: LX, XA, and System21 All-Hands Call
Print
27332 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.