Infor LN & Baan Tip: Cost Component Setup

To break down an item’s standard cost, sales price, or valuation price, use cost components. With cost components, you can compare estimated and actual costs, calculate production variances, and analyze costs in Standard Cost Calculation.

If cost components are set up in a detailed way, detailed records exist in the Item - Calculated Valuation Prices (ticpr2540m000) session and the Item - Standard Valuation Prices (ticpr3540m000) session. Additional financial integration transactions are created because integration transactions are logged by cost component. A detailed cost component setup also causes additional cost details in domains such as Sales and Warehousing. This increases database growth and makes performance worse, especially during production completion and the item receipt process.

Reduce the number of cost components in the effective cost component structure, which is displayed in the Effective Cost Component Structure (ticpr0112m000) session, as much as possible. The minimum number is three aggregated cost components: one for material, one for operation, and one for surcharges. From a performance point of view, the following is advised:

Reduce the number of cost components

  • One operation cost component for all operation rates.
  • One cost component for all subcontracting rates.
  • One cost component for item and warehouse surcharges.
  • One cost component for actual labor rates (in People). Ensure you only use cost components that are required.

Use aggregated cost components
The standard cost is calculated by (detailed) cost component for a multilevel BOM. A similar calculation of valuation prices (actual prices) would result in a price structure with many cost components, especially for manufactured items. In case of a warehouse transfer, issue to WIP, and so on, postings are made for every cost component. However, this detailed cost information does not add functional value in Warehousing. If you aggregate cost components, the number of cost components in financial transactions is reduced. Therefore, aggregate operation cost, material cost, and surcharges to the three cost components that are defined in the Item - Costing (ticpr0107m000) session

If you do not enter a Standard Cost Component Scheme in the Item - Costing (ticpr0107m000) session, production order costs, production order variances, and surcharges are posted by aggregated cost component. This improves performance and decreases database growth.

Previous Article Manual Processes Are Killing Your Productivity
Next Article Infor ERP Tip: Top 5 Ways Modern Analytics Reduces Spreadsheet Risk & Inefficiency
Print
61846 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Note: The Blocked Operations (tisfc0540m000) session displays the blocked operations.

Introduction

Sometimes a problem occurs that must be solved before an operation proceeds. Examples of such situations are:

  • The quality of an intermediate product must first be inspected.
  • A machine is in repair.
  • A supplier cannot deliver an essential component in time.
  • A customer is late with its payments.

In these situations the operation can get the operation status Blocked.

An operation can be blocked:

  • Manually.
  • Automatically by Quality.

Blocking reasons

Every blocked operation must have a blocking reason. The blocking reason of a blocked operation has two purposes:

  • To indicate why the operation is blocked.
  • To determine which actions you can no longer perform on the operation.

Types of blocking

The following actions can be blocked by means of a blocking reason:

  • Reporting a quantity completed.
  • Reporting a quantity rejected.
  • Reporting a quantity to be inspected.
  • Reporting an operation completed.

You normally carry out these actions in the Report Operations Completed (tisfc0130m000) session.

You can define blocking reasons in the Blocking Reasons (tisfc2100m000) session.

Manual blocking

Use the Report Operations Completed (tisfc0130m000) session to block an operation. When you block an operation, you must also enter a blocking reason. If Quality has already blocked the operation, you can only enter a blocking reason, which is more restrictive than the blocking reason of Quality.

Blocking by Quality Managem