Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i
Next Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Print
83745 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Define Inventory transactions for issuing components to the shop and receiving finished items. See the Inventory help text for examples of transactions.

  • Transaction type I - Single Issue to Shop Order. Use this transaction type to issue one component at a time. Use this for high-value items that are marked as Must Single Issue on the Item Master file.
  • Transaction type M - Multiple Issue to Shop Order. Use this transaction type to issue all the components as listed in the Shop Order, in one transaction. Note that this transaction type does not issue Must Single Issue items.
  • Transaction type S - Receipt from shop. Use this transaction type to receive the finished item into stock and update the shop order accordingly. 

The Shop Order Lot/Location Allocation program is an alternative to using the above Inventory transactions. Use this when the item is finished, and you want to review exactly what was used to make it. You can review the components as allocated, make any changes, and finally accept the finished order.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.