Infor LN & Baan Tips & Tricks for OPERATIONS: Creating a Purchase Order with Subcontracting

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. Select the business partner in the Business Partner field, Press Tab. Note: Infor LN populates the default data for the selected business partner in the other fields of the purchase order header.
  4. Select the order type for subcontracting in the Order Type field, purchase office in the Purchase Office field, and the related order series in the Order field.
  5. Click New on the Order Lines tab and select your subcontracted price item in the second segment of the Item field.
  6. Specify the required quantity in the Ordered Quantity field, price of the item in the Price field and click Save.
  7. Click the Approve button to approve the purchase order. The purchase order Status is updated to Approved.
  8. Verify that the material to be sent to the subcontractor is updated on the Material Supply Lines tab.
  9. Select the material line on the Material Supply Lines tab and click Actions > Generate Supply Order.
  10. Select the generated supply order line updated in the Supply Order Line field on the Material Supply Lines tab and click References > Supply Lines. The Warehousing Order (whinh2100m100) session is displayed.
  11. Select the outbound order line on the Outbound Lines tab and click References > Status Overview. The Outbound Line Status Overview (whinh2129m000) session is displayed.
  12. In the Outbound Line Status Overview (whinh2129m000) session, ensure that the Generate Outbound Advice and the Release Outbound Advice activities are automatically executed.
  13. On the specific menu, click Freeze/Confirm. The Shipment Lines (whinh4131m000) session is displayed.
  14. Select the shipment line and click Confirm. The shipment line Status is updated to Confirmed on the Status tab.
  15. Verify that the Line Status is Shipped for the outbound order line on the Outbound Lines tab in the Warehousing Order (whinh2100m100) session.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Cash Flow Statements (tfgld 0123m100)
Next Article Infor LX/BPCS Tips & Tricks for EXECUTIVES:
Print
36960 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Companies can decide to involve a subcontractor and subcontract part of their activities. The subcontractor carries out the work and returns the products to your company.

In Infor LN, subcontracting is considered as purchasing labor from a third party. Therefore, if a manufacturer wants to subcontract work, he must generate a purchase order to start the subcontracting process. These are the types of subcontracting:

  • Subcontracting with material flow
    • Operation subcontracting: For operation subcontracting, a part of the production process (one or more operations) is subcontracted.
    • Item subcontracting: For item subcontracting, an item's entire production process is subcontracted. Therefore, it is always used with material flow support.
  • Subcontracting without material flow: The simplest form of subcontracting is to generate a subcontracting purchase order to record the operations outsourced to a subcontractor. The subcontracting purchase order only represents the administrative handling of the subcontracting process. When the subcontracted item is received back from the subcontractor, you must close the subcontracting purchase order, which initiates the production process.
  • Unplanned subcontracting: Unplanned subcontracting is applicable when you subcontract after generating a production order. For unplanned subcontracting, a purchase order is generated from the production order and the material supply lines are populated by Shop Floor Control.
  • Service subcontracting: For service subcontracting, work on an item to be maintained or repaired is subcontracted. This work entails the entire repair process, or only a part of it. Service subcontracting can be used with or without material flow support.

To start the subcontracting process, a purchase order is required.