Infor LX & BPCS: Explore IDF Programs

IDF (Infor Development Framework) configures your view of the application data without modifying the core application and its supportability. In version 8.3.4 and higher, IDF programs provide the replacement for most of the 300 series inquiry programs. Starting with version 8.4, Infor has added 100 series maintenance programs such as Item Master, Vendor Master, and Customer Master. With IDF, navigation drill-downs are far superior to any green-screen presentation of the data.

Included with IDF are several interfaces including:

  • PowerLink – A Windows-based client for end-users
  • Link Manager – A Windows-based environment administration client for importing environments, starting and stopping environments, and installing Fix Patches
  • Net-Link – A browser-based client (used by LX when running with SiW)
  • System-Link – A XML-based interface for processing transactions from external sources

The IDF ISO includes several components:

  • All of the above interfaces
  • Enterprise Integrator – for customizing IDF components and creating new business objects
  • EGLi – Enterprise General Ledger
  • CRMi – Customer Relationship Management


Don't see what you're looking for? Crossroads RMC provides additional Crossroads MES IDF Reports in the areas of Efficiency, Downtime, Machines, Operations, Parts, Orders, Quality, Receipts Work Centers, and more!

For more information please contact Anthony Etzel

Previous Article Infor LN & Baan: Trying to make your shipping labels generically work for all of your customers?
Next Article Infor LX & BPCS Tip: Customer Type
Print
27470 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.