Infor LX & BPCS Manufacturing Tip: Production Register Listing

Use the Production Register Listing screen, JIT610D1-01, to print an edit list of the labor tickets that you added or updated. Use this report to see the data to post before you actually perform the update. After you print the edit list, you can go back to Production Reporting (JIT600) and change the data before you post the batch. The program assigns a number to each production report that you posted in JIT600. You can use JIT600 to reference the production report that you want to update. Access: Specify Post on Production Reporting, JIT600D1-01.

Previous Article Infor LN & Baan Tip: Remove Posted Payment/Direct Debit Batches
Next Article Increase Production by 10-20% - It's Simple!
Print
28755 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.