Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Previous Article Infor LX & BPCS Tip: Changing an item to non-inventory
Next Article Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?
Print
61882 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.