BPCS/LX Tip of the Week: Alternate Items

How can I use an alternate item on a shop order? 

 

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Previous Article Baan/LN Tip of the Week: Negative Inventory
Next Article BPCS/LX Tip of the Week: Inventory Control
Print
56096 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.