Infor LX & BPCS Tip: What is IDF and Why Do I Need It?

The Infor Development Framework (IDF) re-architects the way a user interacts with the application by providing an efficient, task-oriented process to view the application information that is contained within Infor LX. IDF enables users to configure their view of the application data without modifying the core application and its supportability.

The examples below describe how users can configure their display of data and maximize overall productivity:

  • Arrange application information into multiple groupings and sequences that make sense for the job.
  • Hide information that does not apply to a particular job or task.
  • Filter records to show only the information that applies to the job or task that the user is performing.
  • Customize the information for an individual user, for a group of users, or for all users.

To get more details on how IDF can benefit your company, please contact Anthony Etzel today!

Previous Article Infor LN & Baan | Infor LX & BPCS Tip: Time for the dreaded three words?
Next Article It’s mid-January and IT’S GO TIME!
Print
27412 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.