BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Previous Article Baan/LN Tip of the Week: ERP Setup - Pros & Cons
Next Article BPCS/LX Tip of the Week: Understanding What Goes On Out On The Factory Floor – Part 4
Print
58610 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Note: The Blocked Operations (tisfc0540m000) session displays the blocked operations.

Introduction

Sometimes a problem occurs that must be solved before an operation proceeds. Examples of such situations are:

  • The quality of an intermediate product must first be inspected.
  • A machine is in repair.
  • A supplier cannot deliver an essential component in time.
  • A customer is late with its payments.

In these situations the operation can get the operation status Blocked.

An operation can be blocked:

  • Manually.
  • Automatically by Quality.

Blocking reasons

Every blocked operation must have a blocking reason. The blocking reason of a blocked operation has two purposes:

  • To indicate why the operation is blocked.
  • To determine which actions you can no longer perform on the operation.

Types of blocking

The following actions can be blocked by means of a blocking reason:

  • Reporting a quantity completed.
  • Reporting a quantity rejected.
  • Reporting a quantity to be inspected.
  • Reporting an operation completed.

You normally carry out these actions in the Report Operations Completed (tisfc0130m000) session.

You can define blocking reasons in the Blocking Reasons (tisfc2100m000) session.

Manual blocking

Use the Report Operations Completed (tisfc0130m000) session to block an operation. When you block an operation, you must also enter a blocking reason. If Quality has already blocked the operation, you can only enter a blocking reason, which is more restrictive than the blocking reason of Quality.

Blocking by Quality Managem