Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

George Moroses 0 57168 Article rating: 5.0
  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.

Flexfab Goes Live with Crossroads Data Collection in China

Kathy Barthelt 0 34748 Article rating: 5.0

Flexfab Horizons International, Inc, a global leader in the manufacturing of high performance silicone and other advanced polymer products, goes live with Crossroads RMC’s Data Collection Solution, Web Collect, formerly RMC3, in their China facility. This represents the 3rd data collection go live for the Crossroads data collection solution within Flexfab with the US and UK going live in 2018. All installations focused on improvements in warehouse management in Infor LN 10.6. Applications implemented included Receiving, Inspections/Approvals, Putaway, Stock Transfers and Stock Inquiry.

Crossroads RMC is proud to partner with an American manufacturer of diagnostic healthcare

Integrated freight management solution for Infor LN 10.5.2 Cloud implementation

Kathy Barthelt 0 40334 Article rating: 5.0

An American manufacturer of diagnostic healthcare has selected the RMCship solution from Crossroads RMC to streamline their shipping process on Infor LN 10.5.2 in the cloud. They went live with one site running RMCship in June of 2019 and 3 more sites to follow by end of year. They will use RMCship to increase accuracy by eliminating manual steps and streamlining their operations.

Hunter Douglas Architectural Products Selects Crossroads RMC for LN 10.6 Upgrade Project

LN Upgrade 10.6

Kathy Barthelt 0 34337 Article rating: 5.0

Hunter Douglas, the world leader in window coverings and a major manufacturer of architectural products, has selected Crossroads RMC for their LN 10.2.1 to 10.6 upgrade project. Hunter Douglas has been an LN user for years, but due to a requirement from their parent organization to modernize their hardware/infrastructure, it was decided to update their ERP version as well. Phase 1 of the project will consist of a base technology upgrade with a Phase 2 planned for 2020. Phase 1 Go-Live is slated for January 1, 2020.

To learn more about our Infor LN & Baan Consulting, contact us at: 800.762.2077, email Kathy Barthelt, or visit our Services webpage.

Infor LN & Baan Tip of the Week: The Production Bill of Material – 10.7

Kathy Barthelt 0 173240 Article rating: 5.0

The production bill of material is globally specified at the company level. It can be used as a source for the definition of the local material lists, such as:

  • The production model in the repetitive module.
  • The production model in the job shop module.
  • The subcontracting model in the subcontracting module.

The production bill of material can be generated through the engineering bill of material. The new production bill of material differs from the old bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The material line excludes logistic data (no warehouse nor routing operation).

The production bill of material is not mandatory.

Production bill of material revisions:
The production bill of material is revision controlled. The objective of the revision is to control the changes to the bill of material over time.

The P-bom includes this revision-related data:

  • Revision number
  • Effective date and Expiry date
  • Status (New, Approved, Expired)
  • Creation date and Created by: user
  • Approval date and Approved by: user
  • Expiry date and Expired by: user
  • Source information

On Time Orders: OTTO - The Right Tools!

George Moroses 0 35352 Article rating: 5.0

Your business doesn’t run without the right people and processes in place, but in order for people to manage the right things at the right time, they need tools... the RIGHT tools

OTTO helps manufacturing plants consistently meet customer commitments, allowing supervisors and managers to spend more time analyzing, making decisions, communicating, and coordinating. We can prove that OTTO is the right tool for the job.

Give it a test drive for 30 days at no charge and see immediate results.

Contact George Moroses today to learn more.

First5859606163656667Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Streamline Your Audit Process: How Crossroads RMC and Avalara Ensure Compliance and Confidence

Streamline Your Audit Process: How Crossroads RMC and Avalara Ensure Compliance and Confidence

Be Audit Ready with Crossroads RMC and Avalara

Managing reports and preparing for audits can be incredibly time-consuming and laborious. It involves extracting data from multiple sources, consolidating information, and rectifying any discrepancies. These tasks often drain resources away from revenue-generating activities.

Fortunately, Avalara offers a comprehensive solution with robust reporting capabilities, drastically reducing the time required for these processes from weeks or months to mere minutes.

Avalara serves as a centralized repository of sales tax information, ensuring accuracy and consistency across all systems involved in the compliance process.

Jean Treimanis, CFO: “I feel confident with what we can provide to any state auditor who comes in. And we can do it remotely because they can access my information easily over the internet.”

Through seamless integrations with Infor LN (ERP LN), Baan, Infor LX (ERP LX), and BPCS, Crossroads RMC and Avalara ensure smooth operation and compliance.

To discover how Avalara and Crossroads RMC can streamline your audit readiness and save time and money while ensuring complete business compliance, please refer to the Avalara Audit Risk Infographic and contact Crossroads RMC to schedule a brief discovery call.

800.762.2077

Print
13190 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories