Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 32035 Article rating: 5.0

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:...

Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?

Kathy Barthelt 0 23322 Article rating: 5.0

Yes, this is possible, by following the steps below:

1. Maintain a batch

2. Maintain an invoice headerexport it, add an additional invoice header to the Excel file, and import it

3. Maintain an invoice line for the first invoice, export it, add additional invoice lines to the Excel file and import it
 

Below the above steps are described in detail...

Infor News You Can Use | The business case for moving your ERP to the cloud and choosing MT deployment

Kathy Barthelt 0 11556 Article rating: 5.0

As more companies invest in cloud computing for their business software and migrate their ERP systems to the cloud, many are considering whether single-tenant or multi-tenant cloud deployment is the best choice.

In this executive brief, Infor outlines insights from the analyst community on the growth of cloud technology, key distinctions between single- and multi-tenant deployments, and why the multi-tenant option for ERP may be the best move for your business.

Learn more>

Tick-Tock... It's time to get more out of your ERP

Crossroads RMC 0 9608 Article rating: 5.0

As crazy as it sounds, we’re about to enter the 2nd half of 2024. How are you doing on your 2024 goals? Planning for 2025 projects?

Maybe it's time to get more out of your Infor ERP system.

⇒⇒ TIME TO UPGRADE?

Is an upgrade to the latest version of your ERP the goal for 2024/2025? If so, Crossroads RMC brings 40 years of industry experience to the table to ensure that your upgrade achieves the results you’re looking for and does so on time and within budget.

Crossroads RMC's team of expert consultants will:

  • Review your custom components to see what can be eliminated
  • Provide an analysis of the specific benefits that your company can achieve by upgrading
  • Train your users on the latest functionality
  • Support your users on the old version while the project team focuses on the upgrade project
  • Handle the entire upgrade project from start to finish
  • Supplement your existing project team with 1-2 key resources
  • Develop the integration to that 3rd party system that is a MUST-HAVE when you upgrade


⇒⇒ NOT UPGRADING?

Infor LX/BPCS Tips & Tricks for FINANCE: Prevent Voiding of Selected Invoices

George Moroses 0 16004 Article rating: 5.0

This enhancement prevents users from voiding invoices after they have been selected for payment. If a user selects an invoice for payment and another user voids the invoice during the payment process, it can produce erroneous and duplicate records. The ACP500 programs were modified to check the status of an invoice before it can be voided. If the invoice has been selected for payment, a message is generated, and the invoice cannot be voided.

Infor LX/BPCS Tips & Tricks for TECHNOLOGY: Update User Security in IDF

George Moroses 0 18248 Article rating: 5.0

Automatically synchronize security changes from LX to IDF, replacing CPYSECIDF. This new process synchronizes users in IDF with those in core LX security whenever a user’s security settings are changed. When a user is deleted from an LX environment, they can also be automatically removed from the IDF environment. Changes to a user’s access to programs in LX are mirrored in IDF. Access to Companies, Facilities, and Warehouses are also synchronized. Additionally, when Business Roles or Business Units access is changed, all users assigned to those roles or units are updated in IDF security.

Infor LX/BPCS Tips & Tricks for OPERATIONS: Copy Shop Order

George Moroses 0 18813 Article rating: 5.0

In the Shop Order Selection program, action 3=Copy is available. This action allows copying any shop order except for flow orders or campaign orders. Instead of copying from the parent item's bill of material and routing, the new shop order’s materials and operations will be copied from the selected shop order. Note that if the existing shop order is linked to a customer order or line, this linkage will not be copied to the new shop order.

First1617181921232425Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.