Infor LN & Baan Tips & Tricks for OPERATIONS: WebTop Grid Support Enhancement for MRP320D

George Moroses 0 217 Article rating: 5.0

This enhancement modifies the subfile used in MRP320D Master Schedule Detail Inquiry (SCR001) to expand the subfile with data instead of clearing it as the user pages. This update enables full compatibility with the WebTop 4.8 Grid decorator.

To implement this enhancement, request and apply MR 81428.

Functionally, this change only affects how the subfile is populated to support a deployed WebTop Grid. There is no visible change or user impact in how the program operates.

In summary, the enhancement improves functionality and ensures full WebTop Grid support for the

Infor LX/BPCS Tips & Tricks for FINANCE & TECHNOLOGY: Add Number of Assigned Users to SYS600

George Moroses 0 274 Article rating: 5.0

LX has added the number of users assigned to a Role or Unit to the first screen of SYS600. When displaying the list of profiles on the first screen of SYS600, the list previously included the counts per profile of assigned Roles and Units when the profile was a user. A new column called Users have been added to show the number of assigned users for Roles or Units.

This enhancement provides a quick way to see the number of users assigned to a Role or Unit.

Crossroads RMC launches NextTrack Insights at inPOWER 2025!

Beta testing underway—general availability by year-end.

Nick Olson 0 770 Article rating: 5.0

Big News from inPOWER 2025!

At this year’s event in Wisconsin, Crossroads RMC unveiled NextTrack Insights, our most advanced analytics solution yet. This release marks a major step forward for manufacturers looking to unlock deeper insights from their ERP systems.

The highlight? AI-powered natural language querying. Instead of digging through static reports or dashboards, you can now ask plain-English questions like “Which machines are down?” or “Are we on track to meet production targets for this shift?” and get immediate, actionable answers.

👉 Beta testing is underway, with general availability by year-end.

Learn more...

Infor LN & Baan Tips & Tricks for OPERATIONS: Pegging Material Supply Lines for Operation and Product Subcontracting

Kathy Barthelt 0 1147 Article rating: 5.0

For project pegged production orders, operations can be subcontracted. The material delivered to the subcontractor can be project pegged or anonymous. The subassemblies sent and retrieved are always project pegged. Costing breaks can be applied to direct the costs of the subcontracted operation to a specific project cost account. If (production material) costing breaks are used, a purchase order line's peg can differ from the peg on the material supply line.

For product subcontracting, the subcontracted purchase orders can include materials that inherit the project pegs or can include anonymous materials. The pegged materials are stored in inventory and are shipped to the subcontractor with project pegged orders.

In case of a project pegged order, a peg distribution is linked to the Purchase Order Material Supply Line in the...

Infor LN & Baan Tips & Tricks for FINANCE: Currency Differences

Kathy Barthelt 0 982 Article rating: 5.0

When currency differences are posted, several parameters affect the way the entries in the General Ledger are created. This section explains the possible parameter settings:

  1. Ledger accounts by currency

  2. Writing off currency profits

  3. Fixed exchange rate

  4. Writing off currency differences for anticipated payments


1. Ledger accounts by currency
This parameter is recorded in the Finance Company Parameters (tfgld0503m000) session...

245678910Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.