Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 114763 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 71366 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 52661 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 125877 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 85955 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 78041 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 52697 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 49220 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

First121122123124125126127128130

Tips:  LX | BPCS | M3

Tips: LN | Baan

Anthony Etzel

How to Improve Customer Shipments With OTTO - A Case Study

Setting Industry Service Standards

Shenandoah Manufacturing, a $20 million producer of poultry-raising equipment (heaters and brooders), had been having difficulty for some time shipping orders to customers in a timely manner. They had successfully implemented a popular ERP system and had been using it for more than 3 years, yet the situation didn't improve. 

Customer Service Representatives were complaining about the frequent backorders and late orders. Employees were giving it their best effort, but were frustrated, and customers were threatening to take their business elsewhere.

The company considered installing an APS system as a possible solution, but found implementation would be difficult, expensive, and running the system might be a challenging task as a number of key business practices would have to be changed. A consultant familiar with OTTO suggested they look at that product as an alternative to APS. Several OTTO aspects cited by the consultant convinced them to consider a cursorily review. Specifically:

  • The non-intrusive nature of the product.
  • It's relative inexpensive initial investment.
  • The low overall total cost of ownership.
  • The integration with their ERP system.

The initial demonstration was impressive. OTTO was installed on Shenandoah's server within 45 minutes of arrival and, most impressively, it was fully functional with their real “live” data immediately. Needless to say, the demo was well received. Even more importantly Shenandoah was able to “test drive” the software to prove its applicability before making any dollar commitments.

According to Mark Shank, Information Systems Manager, some baseline measurements were made last year, and it was determined that approximately 50% of their customer orders had shipped on time. As they began using OTTO, on-time order performance rose to 90% for the month. And Shenandoah caught up on its entire backlog and started working ahead on February's orders. In February on-time shipment performance jumped to 92% and subsequently on-time performance has ranged somewhere between 98.3% and 99.5% — well above the 96% goal set by Management.

OTTO provides the means for keeping the whole production organization focused on the few things that have to happen as the ship date approaches to get each order shipped on time. Components that have the potential for delaying an order are identified so they can be managed. Shenandoah's staff, a precious and limited resource, now concentrates on analyzing information and managing the right things at the right time rather than digging out date. To quote one production control individual: “what use to take hours now takes seconds.”

According to Roy Hackett, Plant Manager: "Knowing the right things to pay attention to at the right time — information provided by OTTO — has allowed on-time shipping to be improved by 40 percentage points in less than one month and a lead time reduction from 3-4 weeks to 1-2 weeks on the most important products"

Guessing at what and how much of the work being processed is for real customer orders versus planned orders is eliminated which is especially important when capacity is short during the heavy portion of the business cycle. 

“By focusing on the right things at the right time, production expedites and interruptions are far fewer, production flow is much smoother and productivity is significantly improved.”

Print
30938 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Categories