BPCS/LX Tip of the Week: Alternate Items

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Previous Article Crossroads MES Version 11 Released
Next Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Print
55579 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

123456810Last

Theme picker

Tips: LN | Baan

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:...

Invoicing Methods are a set of parameters that define the types of orders and order lines that can be collected on an invoice, the type of invoice to be generated and the costs to be aggregated on Project invoices and Service invoices.

If options to combine tax codes, departments, sales representatives' line of business area...

First34568101112Last

Theme picker

Categories