Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
31351 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Companies are developing procedures for entering data into an ERP system and for archiving manuals, drawings, specs, and other hard-copy documents. However, in many cases there is no defined procedures to store historical electronic data. Archiving electronic data should be an integral part of your business processes. 

Generally, archiving is the process of moving historical data from the operational environment to a special archive environment. At home, you might move old bank statements from a closet in your study to a box in the attic. At the office, you might store old hard copies of purchase orders in a room far from your own desk. Just because you no longer need the information in your daily work, does not mean you can dispose of the information. In terms of electronic data in your ERP system, archiving means moving historic data from the operational company to a special archive company; in that way, the historic data will be out of your way and safely stored. To free up disk space on your machine after you have archived the data, you can also move the historic data to an external medium.

Archiving strategy:

You can block a warehouse for inbound procedures, outbound procedures, or both. For example, you can block inbound and outbound procedures for a warehouse if the warehouse must be closed temporarily for inspection.

You can impose these types of blockings:

  • Full block: Full block on warehousing procedures.

  • Interactive block: Override blocking allowed except blocks on confirm shipment or confirm receipt.

If you impose a full block on inbound procedures...

Categories