Infor LN & Baan Tip: Defining “Unavailability” in Infor LN

This topic describes the definition of temporary unavailability for resources in a calendar.

Use one of the following sessions:

  • Recurring unavailability
    For recurring unavailability, such as national holidays, define the recurrence in the Recurrences (tcccp0143m000) session. Add that recurrence to the applicable calendar and availability type in the Calendar Recurrences (tcccp0144m000) session, and clear the Available check box for the unavailable days.
    With calendar recurrences you define recurring exceptions in a calendar, and set a time schedule for daily, weekly, monthly, or yearly unavailable time in one action.
  • Unavailable days for all availability types
    To define occasional unavailability, such as a department trip, use the Calendar Non-Available Days (tcccp0119m000) session. What you define here applies to all availability types.
     
  • Unavailable days for a specific availability type
    To define unavailability for a single day, complete the following steps:
  1. Start the Calendar Working Hours (tcccp0120m000) session.
  2. Find the applicable calendar and availability type, and clear the Available check box for a working hours type on the relevant date.
  • Unavailable during a part of a day
    To indicate that part of a day is unavailable, use the Calendar Recurrences (tcccp0144m000) or the Calendar Working Hours (tcccp0120m000) session to specify the time intervals that are available. All other times are considered unavailable. You cannot directly specify an unavailable time interval.

If you defined unavailable dates in the Calendar Non-Available Days (tcccp0119m000) or the Calendar Recurrences (tcccp0144m000) session, in the Calendar Working Hours (tcccp0120m000) session, click Update Calendar.

Note:

  • Unavailability always applies to entire days. If the Calendar Working Hours (tcccp0120m000) session contains multiple time intervals for a single date, and the Available check box is cleared for some intervals and selected for other intervals on the same day, the entire day is unavailable.
  • A calendar recurrence that makes a day unavailable has no effect on the availability of that day in the parent calendar.


It is not useful to define a special availability type for unavailability, because Infor LN does not maintain and update the working hours and the capacity data of a calendar in the Calendar Working Hours (tcccp0120m000) session based on non-available availability types.

Previous Article “Sorry, boss. We can’t help you move the business forward.”
Next Article Infor ERP Tip of the Week: 5 Steps to Managing Sales Tax
Print
30020 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Companies can decide to involve a subcontractor and subcontract part of their activities. The subcontractor carries out the work and returns the products to your company.

In Infor LN, subcontracting is considered as purchasing labor from a third party. Therefore, if a manufacturer wants to subcontract work, he must generate a purchase order to start the subcontracting process. These are the types of subcontracting:

  • Subcontracting with material flow
    • Operation subcontracting: For operation subcontracting, a part of the production process (one or more operations) is subcontracted.
    • Item subcontracting: For item subcontracting, an item's entire production process is subcontracted. Therefore, it is always used with material flow support.
  • Subcontracting without material flow: The simplest form of subcontracting is to generate a subcontracting purchase order to record the operations outsourced to a subcontractor. The subcontracting purchase order only represents the administrative handling of the subcontracting process. When the subcontracted item is received back from the subcontractor, you must close the subcontracting purchase order, which initiates the production process.
  • Unplanned subcontracting: Unplanned subcontracting is applicable when you subcontract after generating a production order. For unplanned subcontracting, a purchase order is generated from the production order and the material supply lines are populated by Shop Floor Control.
  • Service subcontracting: For service subcontracting, work on an item to be maintained or repaired is subcontracted. This work entails the entire repair process, or only a part of it. Service subcontracting can be used with or without material flow support.

To start the subcontracting process, a purchase order is required.

Categories