BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees
Print
54304 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.