Baan/LN Tip of the Week: Warehouse Material Movement / Problems With the Inventory Structure Table (whinr150)

This has come up as an issue during various stages of warehouse material movements – transfers, outbounds, shipments. We have seen it right up to 10.4. The inventory structure table (whinr150) becomes a problem. The error points to that table, but users are lost as to how to fix it.

In the session Units by Unit Set many companies let the field Storage default to Yes. If the UOM is not intended to be used in inventory then that setting should be No. 

If an item is purchased in UOM different from the inventory unit and the setting is Yes then LN adds a record in that UOM to the inventory structure table. It is that record that causes problem later.

The session has an option to change the value of the storage field. Specific > Convert Use for Storage. This option works both ways and will correct all inventory in the UOM range. 

Should a user receive an error that references inventory structure table then the solution is to check that session to see if an odd UOM exists in it. If so use the Convert Use for Storage to correct the problem.

Previous Article Baan/LN Tip: Disabling Unused Functionality in LN
Next Article Crossroads is proud to work with Johnson Crushers International on their LN re-implementation to 10.6
Print
77974 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.