Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Manufacturing Tip: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days. Backward Scheduling Process The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.

2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours

3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100

4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.

5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Backward scheduling is supported in all shop order release programs (SFC500, SFC550, and FAS510). Backward scheduling is recalculated if a shop order is maintained through SFC500 when the due date or the required quantity is changed; however, you cannot enter move and queue times through the maintenance program when adding an operation to the shop order.

Previous Article Infor LX & BPCS Tip: What is IDF and how could it make my life easier?
Next Article Infor LN & Baan Manufacturing Tip: All About Routings
Print
26517 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Enhances purchase order efficiency by automatically calculating the Vendor Delivery Date based on user input.

  • When a purchase order line is created, the user enters the item, order quantity, and Due Date.

  • LX automatically calculates the Vendor Delivery Date, adding buffer time for quality control, testing, and inspection activities.

  • If the Due Date is revised, an informational message prompts the user to review and potentially update the Vendor Delivery Date.

Enhancements:

  • A new PUR820 system parameter enables automatic recalculation of the Vendor Delivery Date.

  • Instead of a manual reminder, PUR500 now issues a message: “Vendor Delivery Date recalculated,” showing the updated date.

Benefits:

  • Eliminates the need to manually review and update the Vendor Delivery Date.

  • Removes the need to delete and recreate PO lines to trigger automatic date calculation.

Enables integration between LX and Infor OS Federation Services (IFS) to automate user provisioning.

  • Bi-directional user synchronization between Infor OS and LX:

    • Infor OS user creation or changes automatically create or update users in LX.

    • IBM i user profiles can be created if needed.

    • Updates to SYS600 user data are reflected in Infor OS.

  • Security Role Integration:

    • LX Security Roles and Units are published as IFS Security Roles via SyncSecurityRoleMaster BODs.

    • LX receives inbound SyncSecurityUserMaster BODs from IFS to create or update user records in SYS600.

    • SYS600 Exit Points trigger ProcessSecurityUserMaster BODs to request user creation or updates in IFS on behalf of LX.

Available Versions: 8.3.5, 8.4.1, 8.4.2

FirstLast

Tips: LN | Baan

Categories