Infor LN & Baan Tip of the Week: LN 10.7 - Inventory Check for Sales Orders

In previous releases, the Check Inventory Sales Order (tdsls4217m000) session was used to provide planned delivery dates to sales order lines by performing ATP checks only during order entry.

The Check Inventory Sales Order (tdsls4217m000) session has been enhanced to support the ATP recalculation of planned delivery dates. ATP checks can now be run on sales order lines with the Order Promising Status set to Accepted. Simulation capabilities and exclusion of already advised sales order lines are also offered.

The new functionality can be enabled for a combination of item and business partner. At sales order line level, the option to disable the recalculation is always available.

Previous Article Infor LX & BPCS Tip of the Week: LX 8.4 Enhancement – Company Security for ACR510
Next Article Infor LX & BPCS Tip: LX 8.4 – Manufacturing Field Size Expansions
Print
58040 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.