BPCS/LX Tip of the Week: Indirect Time Reporting

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

Previous Article Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN
Next Article Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items
Print
59506 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

If you setup the “From” and “To” Location fields in the Work Center file, this will determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to Infor LX.

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have set up your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished, and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are set up and what transactions along with their frequency are captured.