BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 1

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up these fields will have an impact on how you report transactions and what is seen on the SO inquiry screen.

Previous Article Baan/LN Tip of the Week: ERP Setup - Pros & Cons
Next Article Crossroads RMC Maintains Preferred Partner Status With Honeywell / Intermec for 2016
Print
62948 Rate this article:
5.0

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Use this session to define simulated purchase prices for purchased items per site.

Field Information:

  • Cost Calculation Code - price calculation code
  • Item

The raw materials, subassemblies, finished products, and tools that can be purchased, stored, manufactured, and sold.

An item can also represent a set of items handled as one kit, or which exist in multiple product variants.

You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:

  • Cost items (for example, electricity)
  • Service items
  • Subcontracting services
  • List items (menus/options)
     
  • ​Site - The site for which the purchase price is simulated.
  • Purchase Currency - The currency of the simulated purchase price.
  • Simulated Price - Purchase price

The simulated purchase price and currency are recorded twice.

  • Simulated Price Multi Currency - The purchase price in multiple currencies.

The simulated purchase price and currency are recorded twice. The amount in this field is related to the price of the supplier.

  • Unit - Purchase price unit
  • Cost Component - The cost component that must be of the type Material Costs.

Note: The cost component specified in this field does not become part of the standard cost detail structure if it is part of the cost component scheme of the selected item. If calculations are performed with a calculation code not used for actualization (simulations only), the simulated purchase price is mapped to the cost component defined in the records for this session.