Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Manufacturing Tip: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days. Backward Scheduling Process The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.

2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours

3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100

4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.

5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Backward scheduling is supported in all shop order release programs (SFC500, SFC550, and FAS510). Backward scheduling is recalculated if a shop order is maintained through SFC500 when the due date or the required quantity is changed; however, you cannot enter move and queue times through the maintenance program when adding an operation to the shop order.

Previous Article Infor LX & BPCS Tip: What is IDF and how could it make my life easier?
Next Article Infor LN & Baan Manufacturing Tip: All About Routings
Print
26529 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

These programs are used to capture and post shop floor information. Labor reporting, machine time, etc. can be captured by either program. The key difference is that one will also capture the production receipt and backflush components. Based on your company information / transaction process, one of these programs will most likely be used daily to capture current shop floor data. You can use the shop packet labor ticket for the manual recording, and the keying of the data. Alternatively, you can incorporate an automated method like an MES solution to capture the data and streamline the process.

The bubble number is maintained at the component level for each component defined on the Bill of Material. It is an extra user-defined reference number that you can use to re-sequence the maintenance screen display or bills of material listings.

In Infor LX, the system displays the bubble number for the existing child items. Engineering drawings often use a bubble number at the component level on the drawing so that same bubble number can be used on the Bill of Material for a link of the component to the drawing. Alternatively, you may use it simply as a method to sequence the BOM.

Be careful of how you assign the number. It is a good idea to assign the number with a consecutive count by 10 leaving room to allow for component additions to the Bill of Material.

FirstLast

Tips: LN | Baan

Categories