OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
27771 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).