BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees
Print
54319 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

BPCS/LX Tip of the Week: SFC600

In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.