Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
16784 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.
FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.