Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
27790 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.