OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
27786 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In Infor LX, based on how your items are set up and on how you structure the Bill of Material, the following are some usages of a bill of material by functioning area:

  • Engineering & QA – change control, product design and specifications
  • Manufacturing – build instructions , material pick lists
  • Accounting – product costing
  • Materials Inventory – material and inventory planning
  • Sales – customer order processing
  • Production Scheduling – item scheduling (also a component of an MES solution)
In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.