Baan/LN Tip of the Week: Company Calendar

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

Previous Article BPCS/LX Tip of the Week: SFC600 & SFC650
Next Article Infor and Crossroads RMC are proud to offer a joint webinar on Taking Your Shop Floor Paperless - August 28th, 2014.
Print
74607 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In Infor LX, based on how your items are set up and on how you structure the Bill of Material, the following are some usages of a bill of material by functioning area:

  • Engineering & QA – change control, product design and specifications
  • Manufacturing – build instructions , material pick lists
  • Accounting – product costing
  • Materials Inventory – material and inventory planning
  • Sales – customer order processing
  • Production Scheduling – item scheduling (also a component of an MES solution)
In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.