Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Manufacturing Tip: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days. Backward Scheduling Process The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.

2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours

3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100

4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.

5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Backward scheduling is supported in all shop order release programs (SFC500, SFC550, and FAS510). Backward scheduling is recalculated if a shop order is maintained through SFC500 when the due date or the required quantity is changed; however, you cannot enter move and queue times through the maintenance program when adding an operation to the shop order.

Previous Article Infor LX & BPCS Tip: What is IDF and how could it make my life easier?
Next Article Infor LN & Baan Manufacturing Tip: All About Routings
Print
26568 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

FirstLast

Tips: LN | Baan

Categories