Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
16803 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Defining the Product Routing first requires the items to be setup in the Item Master file. Other master files also need to be defined prior to creating the routing.
These include:

  • The Facility defined with a SYS program
  • The Warehouses defined with an INV program
  • Locations defined with an INV program
  • The Machines (required if using capacity planning or an MES interface) defined with an MDM program

After the above data is set up, the Department file and Work Center files can be setup in MDM. Now you are ready to define a product route.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

 

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.