Baan/LN Tip of the Week: Safety Time


You can add safety time in the item master for the item. This will add the number of days safety time to the order lead time thus bringing the order in x number of days early. (x is the safety time).

The safety time is on form 4 of the item master in Baan IV and in Item Ordering Data – Generation I tab in Baan V and LN.

Previous Article BPCS/LX Tip of the Week: How does ERP LX establish costing for purchased items?
Next Article BPCS/LX Tip of the Week: Batch Allocation
Print
99502 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 