Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Event / News

Flexfab Expands Their Use of Crossroads RMC Data Collection for All LN Installations Globally

Data Collection News

Flexfab Horizons International, Inc, a global leader in the manufacture of high performance silicone and other advanced polimer products, has made the decision to expand their use of Crossroads RMC’s Data Collection Solution, RMC3, to their China location. The initial implementations in Nottinghamshire, UK and the United States took place in 2018, and the China implementation is expected to be completed by Q2 of 2019. All installations focus on improvements in warehouse management in Infor LN. Applications implemented include Receiving, Inspections/Approvals, Putaway, Stock Transfers and Stock Inquiry.

Previous Article Crossroads RMC partnered with Electrolux Corporation to Connect Baan IVc4 to Vertex 8.0 (O Series)
Next Article BPCS/LX Tip of the Week: Facility Period Close
Print
27212 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Defining the Product Routing first requires the items to be setup in the Item Master file. Other master files also need to be defined prior to creating the routing.
These include:

  • The Facility defined with a SYS program
  • The Warehouses defined with an INV program
  • Locations defined with an INV program
  • The Machines (required if using capacity planning or an MES interface) defined with an MDM program

After the above data is set up, the Department file and Work Center files can be setup in MDM. Now you are ready to define a product route.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

 

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

FirstLast

Tips: LN | Baan

Categories