Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

Previous Article BPCS/LX Tip of the Week: Actual Costs for Manufactured Items
Next Article Baan/LN Tip of the Week: Switching to a Difference Series
Print
32234 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.