Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC

Crossroads RMC Takes Polar to LX 8.3.4

Polar Beverages, the largest independent soft drink bottler in the United States, went live on Infor LX 8.3.4 on January 16, 2017. Polar partnered with Crossroads RMC for this important technology initiative. Included in the implementation were the Finance Supply Chain and Manufacturing modules. Phase 2 will include Adirondack Beverages, a subsidiary of Polar. This project will begin in Q3 2017.

Previous Article BPCS/LX Tip of the Week: Handwritten Inventory Tickets
Next Article Crossroads RMC, in partnership with Infor, takes Yupo to LX 8.3.4
Print
30707 Rate this article:
No rating
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.