Baan/LN Tip of the Week: Make Your ERP Work FOR You - Streamline Your Processes

Such lofty goals you had when you implemented your ERP system. It was going to be like pressing the “Easy Button”…  then it wasn’t.

What happened? In some cases, decisions were made to implement the system “just like we used to run our old system”. Great idea? Not so much. Your business changes, and your business software needs to change as well.

Are you using the ERP system, but everything seems cumbersome and takes more time than its worth? 

Ask yourself these questions:

  • Have you looked at streamlining your processes?
  • Can you automate a step or two and eliminate some manual keying?
  • Can you add barcoding to avoid keying in some information altogether?
  • How about automating the printing of some reports?

Now is the time to sit down and really review the steps required to complete the task and think out of the box a bit. Soon you can develop your own streamlined process to get the job done quickly and efficiently.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Inventory Transactions
Next Article BPCS/LX Tip of the Week: Inventory Period Balance Freeze
Print
80212 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.