Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN

In Baan IV, a distinction is made between the actual ERP system and a separate planning tool which contains the Constraint Planning package. This tool was intended to work with any ERP system, not just with Baan IV. The Enterprise Planning package is now considered to be a package like any other package in Infor LN.

Users of Baan IV could choose whether they wanted to plan their supply in one of the following ways:

  • By using the MPS and MRP modules in the Manufacturing package.
  • By using the RPD and RMP modules in the Constraint Planning package.

Users of Infor LN can only use the Enterprise Planning package. The distinction between the MPS items and MRP items has been abandoned. In Infor LN, all items can be planned by using a combination of master-based planning methods and order-based planning methods.

Previous Article Baan/LN Tip of the Week: Setting Up New Employees in LN
Next Article BPCS/LX Tip of the Week: Indirect Time Reporting
Print
56283 Rate this article:
No rating

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Companies can decide to involve a subcontractor and subcontract part of their activities. The subcontractor carries out the work and returns the products to your company.

In Infor LN, subcontracting is considered as purchasing labor from a third party. Therefore, if a manufacturer wants to subcontract work, he must generate a purchase order to start the subcontracting process. These are the types of subcontracting:

  • Subcontracting with material flow
    • Operation subcontracting: For operation subcontracting, a part of the production process (one or more operations) is subcontracted.
    • Item subcontracting: For item subcontracting, an item's entire production process is subcontracted. Therefore, it is always used with material flow support.
  • Subcontracting without material flow: The simplest form of subcontracting is to generate a subcontracting purchase order to record the operations outsourced to a subcontractor. The subcontracting purchase order only represents the administrative handling of the subcontracting process. When the subcontracted item is received back from the subcontractor, you must close the subcontracting purchase order, which initiates the production process.
  • Unplanned subcontracting: Unplanned subcontracting is applicable when you subcontract after generating a production order. For unplanned subcontracting, a purchase order is generated from the production order and the material supply lines are populated by Shop Floor Control.
  • Service subcontracting: For service subcontracting, work on an item to be maintained or repaired is subcontracted. This work entails the entire repair process, or only a part of it. Service subcontracting can be used with or without material flow support.

To start the subcontracting process, a purchase order is required.